HR 3062
Passed a chamber
Replaces presidential permits for cross-border oil, natural gas, and electricity facilities with a federal certificate of crossing process, and sets a 30-day deadline for approving natural gas trade applications with Canada and Mexico.
Official title: Promoting Cross-border Energy Infrastructure Act
Timeline each lane is a chamber; dates pull from congress.gov actions
House
Introduced
29-APR-2025
Referred
29-APR-2025
Approved by committee
25-JUN-2025
Reported
02-JUL-2025
On the calendar
02-JUL-2025
Passed
18-SEP-2025
Senate
Received
19-SEP-2025
- Requires a certificate of crossing from the Federal Energy Regulatory Commission for oil and gas pipelines, or from the Energy Secretary for electric lines, issued within 120 days after environmental review unless the agency finds the facility is not in the public interest.
- Removes the presidential permit requirement for these facilities and bars the President from revoking existing permits unless authorized by an Act of Congress.
- Requires the Commission to grant natural gas import or export applications with Canada or Mexico within 30 days of receiving a complete application.
- Repeals the Federal Power Act requirement to obtain a federal order before exporting electricity to Canada or Mexico.
- Takes effect one year after enactment, with rulemaking notices due within 180 days and final rules due within one year.
Covers an older version. The newest CRS summary describes the bill as of "Introduced in House" (29-APR-2025); the text has changed since (Engrossed in House, 18-SEP-2025).
CRS is the Library of Congress's nonpartisan research office. Read it on congress.gov- Natural Resources Committee (House)
- Transportation and Infrastructure Committee (House)
- Railroads, Pipelines, and Hazardous Materials Subcommittee
- Energy and Commerce Committee (House)
- Energy Subcommittee
- Energy and Natural Resources Committee (Senate)
Energy
■ 2 R
2 Republicans