← Back to browse
S 1020 Became law

Allows the Federal Energy Regulatory Commission to give licensees of certain hydropower projects up to 6 more years, in three-year-or-shorter steps, to begin construction.

Official title: A bill to require the Federal Energy Regulatory Commission to extend the time period during which licensees are required to commence construction of certain hydropower projects.

Outcome Public Law 119-90
Timeline each lane is a chamber; dates pull from congress.gov actions
House
Received 01-AUG-2025
Passed 21-APR-2026
Senate
Introduced 13-MAR-2025
Referred 13-MAR-2025
Passed 29-JUL-2025
President
Presented 30-APR-2026
Signed 11-MAY-2026
Became law 11-MAY-2026
Key points
  • Covers hydropower projects licensed by the Federal Energy Regulatory Commission before March 13, 2020, and only when the licensee requests an extension and shows good cause.
  • Permits up to 3 consecutive 2-year extensions, adding no more than 6 years beyond the 8 years already allowed under Section 13 of the Federal Power Act.
  • Allows the Commission to reinstate a license that expired after December 31, 2023 and before the date of enactment, with the extension taking effect on the date of expiration.
AI-generated from the Public Law text of 12-MAY-2026 · verify · report an error
Official CRS summary

Current. The Congressional Research Service's summary covers the bill's latest wording (Public Law, 11-MAY-2026).

CRS is the Library of Congress's nonpartisan research office. Read it on congress.gov
Committee referrals (1) Policy area

Energy

Sponsor Steve Daines (R-MT) Cosponsors · 7
■ 6 R■ 1 D
1 Democrat